Skip to main content
Innovative Living: Site Work & Underground Infrastructure in Progress
Project UpdatesNovember 18, 20263 min readDavid Williamson

Innovative Living: Site Work & Underground Infrastructure in Progress

ITDG's Innovative Living flagship in Tucson is well into its first major construction phase. Underground water harvesting infrastructure is installed and covered, all 14 engineered building pads are compacted and complete, and early utility rough-ins are underway.

The concept has been proven on paper. Now it's being proven in the ground.

Our Innovative Living development in Tucson is advancing through its first major construction phase. ITDG's in-house civil division is self-performing the full scope from day one, with no coordination lag.

Site Clearing & Mobilization

From raw land, crews began mass grading, established drainage grades, and set survey benchmarks across all 14 pad locations.

Site cleared and graded

First excavation cuts underway

Mass Excavation

The underground water harvesting system demanded deep, precise trench work running the full site length. Multiple pieces of heavy equipment operated simultaneously — excavators cutting to grade, skid steers prepping trench beds, and equipment managing material across the site.

Civil equipment mobilized across the full site

Full-site excavation and grading in progress

Deep trench preparation

Underground Water Harvesting System

Rather than routing stormwater off-site, the system captures and detains water below grade. This reduces municipal infrastructure load and meets Tucson's water management requirements in a way that improves long-term operating economics of the property.

Large-diameter corrugated HDPE arch pipes were wrapped in heavy geotextile liner, seated in a compacted gravel bed, in a dual-chamber configuration running the full length of the collection zone. ITDG crews handled every scope: excavation, liner, pipe setting, connections, and backfill. The system is now fully installed and covered.

Dual-chamber HDPE water harvesting system — the full run length

Geotextile liner installation with active equipment on site

Water harvesting system pipes seated in lined trench

Inlet distribution box and connection detail

Engineered Fill & Building Pads

All 14 pad locations have received engineered fill: controlled lifts of approved material compacted and tested to bearing capacity specifications. With pads at certified elevation, early plumbing rough-ins are now underway — four rough-ins set so far, with the remaining coordinated into the construction sequence ahead of vertical framing.

Active grading operations across the full site footprint

Utility stub-outs advancing across the site with ITDG site office in place

Engineered fill operations

Where We Stand

The underground water harvesting system is installed and covered. All 14 pads are compacted and at certified elevation. Early plumbing rough-ins are set. The site is moving fast.

Current status:

  • Site clearing, mass grading, and earthwork: complete
  • Underground water harvesting system (dual-chamber HDPE, full site): installed and covered
  • Engineered fill on all 14 building pads: complete
  • Plumbing rough-ins: 4 of 14 set, remainder in sequence
  • Next: Foundation work and vertical framing

This is the first in a series of construction updates as the Innovative Living project advances toward completion. Interested in the development pipeline? Get in touch.

Full Site Photo Gallery

57 photos & videos

1–12 of 57

Tagged Topics

Project UpdatesMulti-FamilyTucson

Share this article

Help spread the knowledge

End of Article
Get Started

Ready to Build?

Project inquiries, RFP requests, or technical questions — our team is standing by.

No obligation. Response within 24 hours.

0.8 EMR Safety
85% Self-Performed
20–30% MEP Savings
90% Repeat Clients