The concept has been proven on paper. Now it's being proven in the ground.
Our Innovative Living development in Tucson is advancing through its first major construction phase. ITDG's in-house civil division is self-performing the full scope from day one, with no coordination lag.
Site Clearing & Mobilization
From raw land, crews began mass grading, established drainage grades, and set survey benchmarks across all 14 pad locations.


Mass Excavation
The underground water harvesting system demanded deep, precise trench work running the full site length. Multiple pieces of heavy equipment operated simultaneously — excavators cutting to grade, skid steers prepping trench beds, and equipment managing material across the site.



Underground Water Harvesting System
Rather than routing stormwater off-site, the system captures and detains water below grade. This reduces municipal infrastructure load and meets Tucson's water management requirements in a way that improves long-term operating economics of the property.
Large-diameter corrugated HDPE arch pipes were wrapped in heavy geotextile liner, seated in a compacted gravel bed, in a dual-chamber configuration running the full length of the collection zone. ITDG crews handled every scope: excavation, liner, pipe setting, connections, and backfill. The system is now fully installed and covered.




Engineered Fill & Building Pads
All 14 pad locations have received engineered fill: controlled lifts of approved material compacted and tested to bearing capacity specifications. With pads at certified elevation, early plumbing rough-ins are now underway — four rough-ins set so far, with the remaining coordinated into the construction sequence ahead of vertical framing.



Where We Stand
The underground water harvesting system is installed and covered. All 14 pads are compacted and at certified elevation. Early plumbing rough-ins are set. The site is moving fast.
Current status:
- Site clearing, mass grading, and earthwork: complete
- Underground water harvesting system (dual-chamber HDPE, full site): installed and covered
- Engineered fill on all 14 building pads: complete
- Plumbing rough-ins: 4 of 14 set, remainder in sequence
- Next: Foundation work and vertical framing
This is the first in a series of construction updates as the Innovative Living project advances toward completion. Interested in the development pipeline? Get in touch.